Base120 · Decomposition
Critical Path Unwinding
Trace longest sequence of dependent tasks determining minimum project duration
When to use
"Use when a project has dependent tasks and you need to find the minimum duration. Identify the critical path — the longest sequence of dependent tasks. Any delay on the critical path delays the project."
Example
"A construction project — foundation (10 days) -> framing (15 days) -> roofing (5 days) is the critical path (30 days). Electrical and plumbing can run in parallel with framing. Speeding up electrical does not reduce total time; only speeding up the critical path does."
Common misuse
"Optimizing non-critical tasks and expecting the project to finish faster. Only critical path tasks affect total duration. Non-critical tasks have slack and can be delayed without affecting the project."